305
54
Hends and Sub-beads.
COMPARATIVE STATEMENT OF THE ESTIMATED AND ACTUAL
EXPENDITURE OF THE COLONY OF HONG KONG FOR THE YEAR 1931
55
Estimated.
Actual.
Increase.
Decrease.
Provisionally
Explanatory Remarks.
Voted.
$
$
$
$
16,952,878 17,055,505.35 1,267,452.64
1,164.825.29
Brought forward
31. PUBLIC WORKS EXTRAORDIN- ARY,-Continued.
Brought forward
2,417,545 2,034,723.20
188,466.07
571,287.87
235,407.00
COMMUNICATIONS.
85 Patrol Path from Lin Ma Hang to
Shataukok
25,000
86 Reconditioning of Roads
80,000
15,090.89 29,916.69
87 Widening Kam Tin Road to 20 feet...
6,000
9,909.11
83.31 6,000.00
MISCELLANEOUS.
88 New Telephone Switch Board for Tai
Po Police Station
2,600
89 Un Long Nullahs and Improvements... 90 Tai Po Land Office European Lavatory
and Small Store
3,000
2,996.70
11
1,255
1,255.00
91 Compensation and Resumptions
3,000
510.10
92 Windmill for irrigation purposes
3,000
2,600.00
8.30
2,489.90
3,000.00
93 Arms Grilles for New Territories
Police Stations
3,600
1,917.00
1,683.00
| | | | | │
WATER WORKS.
94 Improvements to Fan Ling Water
Works
5,000
4,904.08
635.97
I
SUPPLEMENTARILY VOTED.
HONG KONG.
COMMUNICATION.
95 Barker Road, Improvements from
Stubbs Road to Victoria Hospital...
MISCELLANEOUS.
90 Hong Kong Arsenal Yard
KOWLOON.
2,023.47
2,023.47
263,741.00
263,741.00
MISCELLANEOUS.
97 Traffic Improvement at Traffic Circus,
Tsim Sha Tsui Wharf
98 Resumption at Fanling
3,327.36
8,324.00
3,327.36 8,324.00
99 Electric fittings for hired Sanitary
Department Quarters at K.I.L. 1901
784.14
784.14
100 Resumption of Mr. Tse Tsan Tai's
Building at Seeton, Tsun Wan
101 Additional 100 line Telephone Ex- change Switchboard for Kowloon
Total Public Works Extraordinary
Less Increase
5,500.00
5,500.00
458.41
458.41
Surfacing not undertaken.
Postponed.
Postponed.
Fewer resumptions. Postponed.
Over estimated.
Less work done than anticipated.
2,050.00
Found necessary after Estimates approved.
263,741.00
Motion in Council of 3rd September for $2.000.000.
Part of the 1st instalment of $500,000 was paid from Prays East Reclamation
3,328.00
Found necessary after Estimates approved.
8,324.00
do.
827.00
do.
5,500.00
do.
500.00
do.
2,500,000
2,374,931.99
472,624.45
597,692.46
519,677.00
472,624.45
Savings
-
125,068.01
Carried forward
$
19,452,878
19,430,437 34 1,740,077.09
1,762,517.75
[Funda.